Demand and Capacity Management (DCM)

In the Data Space Accelerator, your company takes the role of supplier and Cofinity-X the role of customer. You therefore publish a demand endpoint for Cofinity-X to push to, and you push your capacity group to the endpoint Cofinity-X publishes.

The two exchanges

Each partner is the provider in one direction and the consumer in the other, so both sides need an asset published and a consumer flow configured.

Prerequisites

  • Completed onboarding to Cofinity-X (see Program Overview)

  • A certified EDC connector, registered in the discovery service

  • A signed governance credential

  • A BPNS generated in the Portal - mandatory in DCM, as demand and capacity are tied to a site

Your access and usage policies must carry the DCM values, or the other side cannot negotiate:

Policy

Required constraint

Access policy

Membership: active, granted to your partner's BPNL

Usage policy

FrameworkAgreement: DataExchangeGovernance:1.0

Usage policy

UsagePurpose: cx.dcm.base:1

Step 1: Create Cofinity-X as partner

Set Cofinity-X up as your customer in your DCM application, using the details below.

Company Name

Cofinity-X GmbH

BPNL

BPNLCOFINITYEZFA

BPNS

BPNS00000000P82A

EDC URL

Capacity asset ID

12abc5f9-9721-454f-813d-7f67fedaf66e

Step 2: Create your test master data

Set up the material and the capacity group you will exchange, before running either direction. Both sides must hold the same identifiers, or the link between the two exchanges cannot be made.

Material description

Spark Plug

Material number, customer

MNR-7307-AU340474.002

Material number, supplier

MNR-8101-ID146955.001

Global asset ID

urn:uuid:48878d48-6f1d-47f5-8ded-a441d0d879df

Demand category

0001

Step 3: Publish your demand endpoint as an EDC asset

Register the API that receives material demand as an asset, so Cofinity-X can negotiate for it and push to it.

Step 4: Exchange the data

Cofinity-X pushes a WeekBasedMaterialDemand to the asset you published in Step 3. Confirm in your application that it arrived.

You then send your capacity group back.

Your capacity group data should reference the demand series you received, through linkedDemandSeries. Carry over materialNumberCustomer, customerLocation and demandCategory exactly as they arrived. This link is what demonstrates DCM rather than only that two connectors can move data.

Notify Cofinity-X

Send an email to [email protected] with your EDC endpoint, BPNL and BPNS.

Cofinity-X will run both exchanges with you and validate the payloads against the Catena-X requirements.

Questions or need help? Contact [email protected].